Upcoming Intersection Access Changes on 13th Avenue in West Fargo

 

As project work progresses for the 13th Avenue road reconstruction and infrastructure improvement project intermittent short-term intersection access changes will continue in Fargo and West Fargo.

The timing of these access changes will be weather dependent, and schedules may vary due to longer concrete cure time in the cooler temperatures.

Current intersection closures include:

  • 12th Street E and 13th Avenue intersection (West Fargo): Closed through Saturday, October 20
    • Crews have completed the last concrete pour needed through the intersection today. The intersection will reopen once new concrete has reached design strength, which is anticipated to be achieved by mid-day.
  • 17th Street E and 13th Avenue intersection (West Fargo): Closed through Tuesday, October 23
    • Crews have completed paving the westbound lanes through the intersection and will complete paving the remaining areas of the intersection Thursday and Friday. The intersection will reopen once new concrete has reached design strength.