(Fargo, ND) --  Beginning Monday, August 2nd, crews will start working on phase one of the 13th Ave. S. Concrete Pavement Rehabilitation project from 25th St. to 28th St.

Motorists will be reduced to one lane in each direction in this section. Phase one is expected to take up to 10 weeks.

The overall 13th Ave. S. CPR project extends from 21st St. to 28th St. Following Phase 1, crews will start Phase 2 which involves extending work east on 13th Ave. S. to 21st St.

During CPR projects, crews remove the bad areas of concrete pavement and replace the area with new concrete. Sections of the roadway will re-open to traffic once designed strength has been achieved on the new concrete.